Description: The supplier accepts an order sent by the buyer and sends back an order response. Later, the supplier rejects the order and sends back another order response. The buyer is not allowed to take any further action on a supplier-rejected order. Furthermore, Procurement will ignore any subsequent supplier updates (i.e. order responses) to this order.
Although this scenario is not likely it is shown here because it is possible. However, the second order response that rejects the order will only be processed by Procurement if the order is not fully received by the buyer. If the receive status is Fully Received then Procurement will ignore the order response.
As is the case for the Order Rejected By Supplier scenario above, the buyer is not allowed to take any further action once a supplier rejects the order.